QUESTION 146
Your program has a budget at completion of $1,550,000 and is expected to last one year.
Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete by this time, but due to some vendor delays your program is running just a bit late. Based on this information which is performing worse, the cost or schedule?

 
 
 
 

QUESTION 147
You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the cost performance index for this program?

 
 
 
 

QUESTION 148
A program completes all component projects and all identified benefits are being delivered. However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters.
To ensure the realization of long-term benefits, what should the program manager use?

 
 
 
 

QUESTION 149
Which of the following tools/techniques keep program managers and executives informed of the program’s progress?

 
 
 
 

QUESTION 150
What percentage of communication is nonverbal?

 
 
 
 

QUESTION 151
You are the program manager of the NHQ Program. You are working with your program team to ensure that the work in the program is done accurately and according to scope. You are also reviewing the team inspection process that will need to be done to ensure that the work is being done according to the scope. If the work is found to be defective it will need to be corrected before the program customers can inspect the work. What process are you completing to ensure that the work is done accordingly to scope?

 
 
 
 

QUESTION 152
Martha is sharing her experience of her last project as the project manager. She tells that when she presented customer a formal acceptance and sign-off document, they refused to sign, claiming that the product does not meet their expectation. Taking which of the following steps could have been prevented the situation? Each correct answer represents a complete solution. Choose all that apply.

 
 
 
 

QUESTION 153
A program has a budget at completion of $1,250,000 and has already spent $425,000. The program is running late due to some vendor delays; the program is only 30 percent complete though it was scheduled to be 45 percent at this time. Based on this information how much more money will this program need to finish?

 
 
 
 

QUESTION 154
You are the program manager for your organization and you are dealing with your program stakeholders. You are explaining to them, along with your program team, how certain activities in the program may cause delays in the schedule if the associated risk events come into play. The cost of impact of the risk events are minimal, but the schedule impacts could be bigger. The stakeholders are concerned about delaying the schedule beyond a given due date for the program. They would like you to determine if it is possible to add more labor, use a higher grade of material, or hire some consultants to ensure the risks do not occur in the program. They are not much concerned about the cost of the solution as long as the solution or identified risks do not delay the program completion. What type of risk response are your program stakeholders recommending in this situation?

 
 
 
 

QUESTION 155
A program to implement a new payroll processing system at a healthcare company is nearing completion and is under budget.
What should the program manager do next?

 
 
 
 

QUESTION 156
A program manager is identifying and verifying risks as outlined in the risk management plan. The results will be recorded in which of the following?

 
 
 
 

QUESTION 157
Which of the following increases when one fast tracks the project?

 
 
 
 

QUESTION 158
A multiyear program is ready to conclude. It has achieved all business objectives and is delivering its intended benefits. However, the program sponsor is not willing to sign the formal program closure acceptance document and the program continues to incur operational costs.
What should the program manager do next?

 
 
 
 

QUESTION 159
A Project Manager has been working on quality process of a project at a major electronics manufacturer. This manufacturer is involved with various government and defense contracts as well. The Project Manager discovers that an employee has been reselling some repair material that he has declared as scrap material because they were discontinued, at a small profit on the internet. The item is very costly. What should the Project Manager do?

 
 
 
 

QUESTION 160
A program manager is identifying and verifying risks as outlined in the risk management plan.
The results will be recorded in which of the following?

 
 
 
 

QUESTION 161
In your program you must adhere to Six Sigma as part of your organization’s enterprise environmental factors. There is terminology, reports, and measurements that you are expected to use as part of your program. Six Sigma is an example of what program management process?

 
 
 
 

QUESTION 162
You are the program manager of the OFE Program. You are working with your program team and project managers to ensure that there is consistency in the execution of the program plan. You stress that the work has been planned and now the team must accurately complete the work. You want to ensure that the work is done correctly the first time in the program. What type of process are you stressing to your program team and project managers?

 
 
 
 

QUESTION 163
A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change.
To whom should the change request be presented?

 
 
 
 

QUESTION 164
Robert’s program is slipping on its schedule and management has asked that Robert find a method to compress the duration of the program. What approach could Robert take that would not dramatically add risks to program if he added labor to the effort-driven activities within the program?

 
 
 
 

PgMP Study Material, Preparation Guide and PDF Download: https://www.braindumpsit.com/PgMP_real-exam.html 1

Links:
  1. https://www.braindumpsit.com/PgMP_real-exam.html
Post date: 2022-07-23 11:41:34
Post date GMT: 2022-07-23 11:41:34

Post modified date: 2022-07-23 11:41:34
Post modified date GMT: 2022-07-23 11:41:34

Export date: Sat Apr 5 16:22:55 2025 / +0000 GMT
This page was exported from IT Certification Exam Braindumps [ http://blog.braindumpsit.com ]