Practice Test for AACE-PSP Certification Real 2023 Mock Exam

Prepare For Realistic AACE-PSP Dumps PDF - 100% Passing Guarantee


The AACE-PSP exam is a rigorous test that assesses the candidate's knowledge of project planning and scheduling concepts, techniques, and tools. AACE-PSP exam covers a wide range of topics, including project management fundamentals, schedule development, time management, resource management, and risk management. Candidates must demonstrate their mastery of these topics to pass the exam and earn their AACE-PSP certification.


AACE International AACE-PSP (Planning & Scheduling Professional) Certification Exam is a rigorous examination designed to test the knowledge and competency of professionals in the field of project planning and scheduling. AACE International is a renowned professional association for project management professionals, and their PSP certification program is recognized globally as a mark of excellence in the planning and scheduling profession.

 

NO.63 What is the result of a forward pass calculation?

 
 
 
 

NO.64 Under which circumstance should one perform resource-leveling calculations?

 
 
 
 

NO.65 Time-scaled logic diagrams are

 
 
 
 

NO.66 Which activity is drawn in the incorrect position?

 
 
 
 

NO.67 Theoretically construct a summary activity for activities 2001 through 2004. Using the “normal” schedule, what is the cost of the hammock?

 
 
 
 

NO.68 What does the narrow band at “Y” represent?

 
 
 
 

NO.69 Is activity 7001 pictured correctly in the precedence diagram?

 
 
 
 

NO.70 Identify the minimum project duration.

 
 
 
 

NO.71 Which of the following is NOT required when initially planning a project?

 
 
 
 

NO.72 Which of the following is NOT true?

 
 
 
 

NO.73 If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?

 
 
 
 

NO.74 What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?

 
 
 
 

NO.75 Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

 
 
 
 

NO.76 In its simplest form, what is the main drawback of critical path method scheduling?

 
 
 
 

NO.77 Free float is the

 
 
 
 

NO.78 Which of the following are NOT normally included in the project scope statement, either directly or by reference?

 
 
 
 

NO.79 In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

 
 
 
 

NO.80 The sum of all budgets for work scheduled to be accomplished within a given time period is the
____________.

 
 
 
 

NO.81 The activity with the most total float is:

 
 
 
 

NO.82 In the “normal” schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?

 
 
 
 

NO.83 Which of the following are NOT considerations or constraints of the planning process for construction scheduling?

 
 
 
 

NO.84 If all other work proceeds according to the Baseline plan, how many times will the critical path change?

 
 
 
 

NO.85 Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?

 
 
 
 

Download AACE-PSP Exam Dumps Questions to get 100% Success: https://www.braindumpsit.com/AACE-PSP_real-exam.html 1

Links:
  1. https://www.braindumpsit.com/AACE-PSP_real-exam.ht ml
Post date: 2023-11-15 13:57:35
Post date GMT: 2023-11-15 13:57:35

Post modified date: 2023-11-15 13:57:35
Post modified date GMT: 2023-11-15 13:57:35

Export date: Sat Apr 5 7:32:55 2025 / +0000 GMT
This page was exported from IT Certification Exam Braindumps [ http://blog.braindumpsit.com ]