4/5 - (1 vote)

Best Way To Study For PMI PMI-RMP Exam Brilliant PMI-RMP Exam Questions PDF

Updated Verified Pass PMI-RMP Exam – Real Questions and Answers

QUESTION 137
You are the project manager of RTF project for your organization. You are working with your project team and several key stakeholders to create a diagram that shows causal factors for an effect to be solved. What diagramming technique are you using as a part of the risk identification process?

 
 
 
 

QUESTION 138
A risk manager and project team are managing a software system project, which is expected to be completed within 12 months. The project is currently halfway through, and the team has just delivered the second version of the prototype. During the weekly status meeting, a team member reported that an important stakeholder is facing an issue, which will likely result in a change request that is outside the scope of the current prototype.
What should the risk manager advise the team to do first?

 
 
 
 

QUESTION 139
Management has asked you to perform a risk audit and report back on the results. Bonny, a project team member asks you what a risk audit is. What do you tell Bonny?

 
 
 
 

QUESTION 140
An organization faces immense competition in the market and decides to accelerate a key project. What is the first action for the project risk manager to take?

 
 
 
 

QUESTION 141
The project manager needs to create a risk management plan for a high risk project, but the company’s senior management does not see value in spending time documenting major risks instead of leading the project.
What is the most appropriate action for the project manager to take first?

 
 
 
 

QUESTION 142
A newly assigned project manager is reviewing the project documents with stakeholders to identify opportunities that will fast track the project and realize the financial benefits of early completion. What document should be updated at the end of the review?

 
 
 
 

QUESTION 143
During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.
What should the risk manager do first?

 
 
 
 

QUESTION 144
A project manager identified a risk of communication issues with the client which may impact the project schedule. A member of (he sales team advises that this client prefers face-to- face conversations.
What should the project manager do to avoid this risk?

 
 
 
 

QUESTION 145
A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.
Who should the project manager hold accountable for missing the risks?

 
 
 
 

QUESTION 146
During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.
What action should the project manager take?

 
 
 
 

QUESTION 147
In a complex project, individual risks have been identified with the stakeholders. The project sponsor asks the risk manager about the likelihood of project success. Which risk analysis tool(s) should the risk manager use as a basis for their response?

 
 
 
 

QUESTION 148
The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.
What is this an example of?

 
 
 
 

QUESTION 149
A risk manager for a financial organization is assigned to support a project team in developing a custom software solution to manage loans. Which document should the risk manager request first from the project sponsor to identify major risks?

 
 
 
 

QUESTION 150
A supplier Is delayed in delivering fuel for a project. The project manager anticipated this risk and is requesting fuel from another supplier. When speaking with the other supplier, a new risk appears because fulfilling the order will cause delays with several other projects.
After performing a detailed analysis, what should the risk manager do?

 
 
 
 

QUESTION 151
A project is in the planning phase, and the risk manager establishes the risk management for the project.
Which success factors should be taken into account by the risk manager to establish a successful risk management process for the project?

 
 
 
 

QUESTION 152
A risk on the risk register is triggered. This triggered risk costs US$200,000 to mitigate and will overwhelm the project, causing it to fail if not mitigated. The project manager identifies that there is US$200,000 left in the management reserve.
From which of the following sources should the funds be drawn to cover the risk mitigation?

 
 
 
 

QUESTION 153
You are the project manager for the ABC organization. Your current project has 75 internal stakeholders and 245 external stakeholders. Many of the risks within your project will only affect the internal stakeholders, but several of the identified risk events will affect the external stakeholders. Management would like to know the total number of communication channels in the project. How many communication channels exist in this project?

 
 
 
 

QUESTION 154
At the time the risk register is first prepared, it should contain all the following entries EXCEPT______________

 
 
 
 

Updated PDF (New 2025) Actual PMI PMI-RMP Exam Questions: https://www.braindumpsit.com/PMI-RMP_real-exam.html

         

Related Links: myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt

Leave a comment

Your email address will not be published. Required fields are marked *

Enter the text from the image below